Wycliffe Avenue Reconstruction in Highland Park: Changes Through 2028

The stretch of Wycliffe Avenue that runs across the dam between St. Johns Drive and Lakeside Drive is being taken out and rebuilt as a bridge. The Highland Park Town Council approved a $22,205,303 construction contract with Rebcon at its Sept. 15 meeting, People Newspapers reported. Work was slated to begin in October, with completion targeted for June 2028, weather permitting.

During construction, Wycliffe will be closed between Abbott Avenue and Oak Lawn Avenue. When the fences come down, the crossing at Connor Lake will be higher, narrower and built differently than the road residents have driven for years.

The Road Across the Dam Comes Out

The town's Wycliffe Avenue project FAQ says work will center on Wycliffe between St. Johns Drive and Lakeside Drive. In that stretch, "the existing dam (roadway)" will be removed and rebuilt as a bridge. The town calls the project a safety measure. Its goal is to change the existing dam's classification from "high-hazard" to "low-hazard."

Engineers presented the physical changes to the council in December 2024, as People Newspapers covered at the time. The plan raises the roadway 2.5 feet, builds a weir and a bridge, removes a standpipe, and widens the downstream channel. Here is how the crossing compares today and after the project:

Today After the project
Structure Roadway on top of the dam Bridge with a weir
Road height Current grade Raised 2.5 feet
Lanes on Wycliffe Three Two, plus a dedicated left-turn lane across the bridge
Connor Lake Current water level Same water level kept
Streetscape Current landscaping and walkways Upgraded pedestrian pathways, landscaping and aesthetic improvements

Losing a lane is the change daily drivers are most likely to notice. The town says it ran traffic modeling to address residents' concerns, and that "the analysis shows no significant change in traffic flow under the proposed configuration." The FAQ links two comparison videos, one for current conditions and one for the two-lane layout, so anyone who drives the corridor at rush hour can watch both.

Keeping Connor Lake's water level was a design goal from the beginning. It appeared in the December 2024 presentation, and the town's current FAQ lists it as a benefit that maintains "the community's aesthetic and environmental character." The view from St. Johns should look familiar. The road crossing it will not.

Why the Start Date Kept Moving

This project has been close to starting more than once. Here is the timeline so far:

  1. December 2024. The town presented the plan to residents with an estimated total cost of $21,830,000 and a town share of $6,132,000. Mayor Will C. Beecherl opened that meeting by acknowledging residents' concerns.
  2. August 2025. A People Newspapers story, "Dam and Bridge Reconstruction to Begin in January," reported that the work would start that January. An earlier version of the town's FAQ also listed a January 2026 start.
  3. Later town FAQ. The online FAQ moved the expected start to June 2026, with a construction period of about 20 to 24 months.
  4. Summer 2026. Preparatory utility work narrowed Fitzhugh Avenue to one lane during working hours, from just west of the Katy Trail to Oak Lawn Avenue. Highland Park Department of Public Safety Lt. Lance Koppa told People Newspapers that AT&T expected to finish in mid-July, with Oncor starting after that.
  5. Sept. 15, 2026. The council awarded the $22,205,303 contract to Rebcon, the low bidder, with work slated to start in October and finish by June 2028.

Between the December 2024 estimate and the September 2026 contract, the projected cost rose by about $375,000, a small change for a project this size. The town's share has stayed close to $6.2 million the whole time. Over the same period, the projected start moved from January 2026 to June 2026 and then to October 2026, and the June 2028 completion target is built on that latest start.

The most recent public report, from Sept. 21, said work was "slated" to begin in October. For the actual closure date, check the town's own channels before you plan a route around it.

What Twenty Months Looks Like From the Curb

The FAQ describes closures in phases, not all at once. Portions of Wycliffe Avenue, Fitzhugh Avenue, St. Johns Drive, Lakeside Drive and Turtle Creek Boulevard will see closures or restricted access at different points, and "not all areas will be impacted simultaneously." The town says it will post detours, signage and traffic control as each phase begins.

For homes on or near the work zone, the town has made specific commitments:

  • Access: The town says residents and businesses will keep access throughout the project, including mail and package deliveries, utility service and visitors.
  • Emergency response: Fire, police and EMS will have "immediate and unimpeded access."
  • Parking: Parking near the construction site will be limited to residents only, and the town plans to place crew parking where it affects nearby blocks the least.
  • Site oversight: Work zones will be fenced and signed, with a dedicated inspector and an owner's representative responsible for daily site safety.

Utility work will reach well beyond the bridge. The town plans to relocate and replace its 30-inch Turtle Creek interceptor along with 8-inch water lines and 8-inch and 18-inch wastewater collectors. The City of Dallas will upsize a 10-inch wastewater line to 18 inches and replace a 16-inch water line. Oncor, Atmos, AT&T and Spectrum will move their own lines in coordination. The town expects any service interruptions to be brief and says they will be announced in advance. University Park infrastructure is also part of the upgrade, which is one reason the work connects to so many partners.

The Fitzhugh lane closures this summer, one lane while crews worked and two after hours, are probably the best preview of how phased restrictions will feel on the surrounding streets.

Who Pays, and Why Wycliffe Is One of Several Projects

The project costs about $22 million, but the town's FAQ says roughly 72 percent comes from outside Highland Park. TxDOT is contributing through an 80/20 federal funding match. Dallas County is splitting costs 50/50. The TCEQ provided a grant toward design, and the cities of Dallas and University Park are also contributing. Local tax dollars cover the remaining $6.2 million or so. The design itself was not decided by the town alone. The FAQ says many elements came from resident input and others were "designated by legal necessity." In 2024, the mayor tied parts of the project to stipulations in a pending lawsuit settlement.

Wycliffe was not the only project approved that night. The council also authorized the town administrator to sign construction contracts for the Eastern Avenue Reconstruction Project, the Douglas Avenue Reconstruction Project and the 2026 Drainage Easement Improvements Project. That means four contracts moving at once, across several corridors, heading into the new fiscal year.

The council's own discussion shows how closely members are watching the disruption. At the same meeting, the council approved an updated Master Fee Schedule covering building permits, plan review, water, sewer, solid waste and stormwater drainage, effective Oct. 1, 2026. Council Member Margaret Keliher voted against it and raised concerns about long construction timelines and their effect on residents, People Newspapers reported. If you are planning a renovation of your own during this period, the new permit and plan-review rates already apply.

Where the Updates Will Come From

The town has said it will build a dedicated project website for construction alerts, milestones and FAQs. It has also hired a local strategic communications firm. Updates will appear on the town website, social media, newsletters and Blue Zone notifications. An owner's representative assigned only to Wycliffe will serve as the on-site contact for affected residents.

Phases will shift which of St. Johns, Lakeside, Fitzhugh and Turtle Creek Boulevard is restricted at any given time. For that reason, Blue Zone alerts and the project site will be more reliable than any single map you save today. Kimley Horn's renderings, which the town has shared publicly, show what the corridor is meant to look like once the work is finished.

If you own a home near Connor Lake and are thinking about whether to list before, during or after the Wycliffe work, I'm glad to walk through what showings and timing could look like with phased closures nearby. Christian Holmes is always happy to talk it through. Let's Connect.